Infrastructure: construct or expand
Infrastructure is defined under Appendix 1 of the Native Vegetation Regulations 2017 as:
“infrastructure means—
(a) the infrastructure, equipment, structures, works and other facilities used in or in connection with the supply of water or electricity, gas or other forms of energy, the provision of telecommunications, or the drainage, removal or treatment of waste water or sewage; or
(b) roads and their supporting structures or works; or
(c) ports, wharfs, jetties, railways, trams and busways;”
Infrastructure under Regulation 12 (34) – Infrastructure, includes:
“infrastructureincludes—
(a) flood mitigation works; and
(b) an airstrip; and
(c) a shipping channel; and
(d) a public reservoir.”
For further information see the Fact Sheet - Infrastructure.
If you want to clear native vegetation to expand or construct infrastructure, the requirements that must be met are outlined under Schedule 1, Regulation 12, Clause 34 of the Native Vegetation Regulations 2017.
Can I clear native vegetation for the construction or expansion of a building or infrastructure?
You can clear vegetation incidental to the construction or expansion of a building or infrastructure (and associated services) where the Minister has declared that the clearance is in the public interest and consent under the Planning, Development and Infrastructure Act 2016 has been obtained.
Does this include land under Heritage or Management Agreement?
No, you cannot clear for this purpose on Heritage Agreement or Management Agreement land.
Do I need approval?
Yes, you need to get approval from the Native Vegetation Council.
What do I have to do?
Make sure that your clearing is within the parameters of this activity.
Apply the Mitigation Hierarchy. Are there practical alternatives to clearing, including options that involve no clearing, or clearing vegetation that is less significant or more degraded?
The Native Vegetation Council will assess the clearance application for level of risk to biodiversity and whether there are any other alternatives that involve no clearance, less clearance or clearance of vegetation that is less significant (or has been degraded to a greater extent than the vegetation proposed to be cleared).
If your application is assessed as a ‘low risk’ activity (Level 1 of the Risk Assessment)
Your proposed clearance will be considered low risk if it is for 500 m2 or less of vegetation, or 5 or fewer scattered trees. In the pastoral areas of the state (i.e. NRM Regions South Australian Arid Lands and Alinytjara), the vegetation proposed to be cleared can be up to 3 hectares.
You will need to provide the following to the Native Vegetation Council:
- an online application identifying the
- regulation that applies to your situation
- measures taken to avoid and minimise the proposed clearance
- number and size of any scattered trees to be cleared
- size of vegetation patch to be cleared
- any previous clearance history
- photographs of the site.
The Native Vegetation Council will assess the information against the Mitigation Hierarchy and the requirements of the regulation (you can see these in detail in the Native Vegetation Regulations 2017). If the Native Vegetation Council is satisfied, the Native Vegetation Council will issue an approval and a Significant Environmental Benefit (SEB) offset of $500 will be required.
If any of the following escalating factors are identified in the risk assessment, the application will be automatically raised to the next level (Level 1 to Level 2) of risk and an SEB offset will be required. If there:
- are trees with a trunk circumference of 50 cm or more (30 cm for the pastoral zone and measured at 1 m above the ground); or
- is a high likelihood that the vegetation contains or is habitat for a species listed under the National Parks and Wildlife Act 1972 or a threatened community under the Environment Protection and Biodiversity Conservation Act 1999.
If your application is assessed as a ‘medium to high risk’ activity (Levels 2, 3, and 4 of the Risk Assessment)
If your proposed clearance does not meet the criteria for low risk (Level 1), you will be required to engage an Accredited Consultant to undertake a vegetation assessment of the proposed clearance area. The consultant will prepare a Data Report which must be submitted in addition to the information required for ‘low risk’ applications.
What are my obligations if I am granted approval?
- Undertake clearance within 2 years of approval being granted, unless otherwise specified.
Undertake clearance in compliance with any conditions that apply which are binding and enforceable against the person to whom the approval is granted as well as subsequent owners and occupiers of the land.
Note:
Clearance to maintain infrastructure under Regulation 8(2) may also apply.
What if I want to clear vegetation to maintain existing infrastructure?
You can clear vegetation to maintain infrastructure without seeking approval.
What if my activity doesn't fit this description?
If your proposed clearance does not meet the requirements of this regulation, or another regulation, you can submit a clearance application under Section 28 of the Native Vegetation Act 1991.